Concepts

When studying for the PMI Risk Management Professional (PMI-RMP) exam, understanding how to perform risk weighting and calculate risk priority is essential.

Risk Weighting

Risk weighting involves assigning weights to different risks based on their potential impact on a project. The weight of a risk usually corresponds to its potential impact and the likelihood of it occurring. Risk weighting allows for a more effective prioritization and management of risk.

Risk Priority

On the other hand, risk priority refers to the order in which risks should be addressed based on their overall impact on the project. Risk priority can be determined by multiplying the weight of the risk by the probability of its occurrence.

Example 1

Let’s assume we have three potential risks to a project: Risk A, Risk B, and Risk C. Each risk is given a specific weight:

  • Risk A: 3
  • Risk B: 2
  • Risk C: 1

And the probability of each risk occurring:

  • Risk A: 0.2
  • Risk B: 0.3
  • Risk C: 0.5

The risk priority score for each is then calculated as follows:

  • Risk A: 3 * 0.2 = 0.6
  • Risk B: 2 * 0.3 = 0.6
  • Risk C: 1 * 0.5 = 0.5

From the calculation, Risk A and Risk B are seen as the top priority.

Outline Table

Risk Weight Probability Risk Priority Score
A 3 0.2 0.6
B 2 0.3 0.6
C 1 0.5 0.5

Bear in mind, this is a simple example and real project risks can be much more complex, involving multiple factors and interdependencies amongst risks.

Example 2

Let us consider another example where we have five risks: Risk P, Q, R, S, and T.

Risk Weight Probability
P 5 0.1
Q 4 0.2
R 3 0.3
S 2 0.4
T 1 0.5

The risk priority score for each risk is then calculated as follows:

Risk Risk Priority Score
P 5 * 0.1 = 0.5
Q 4 * 0.2 = 0.8
R 3 * 0.3 = 0.9
S 2 * 0.4 = 0.8
T 1 * 0.5 = 0.5

From the calculation, Risk R should be the highest priority.

Performing risk weighting and calculating risk priority are critical steps in managing risk effectively. They form part of the larger process of risk assessment, which also involves identifying risks, assessing their impacts and likelihoods, developing responses and monitoring and reviewing risks.

To carry out these tasks effectively, a risk management professional needs to have a good understanding of the project, including its objectives, constraints, stakeholders and internal and external environments. They also need good judgment, as risk management often involves making decisions in the face of uncertainty.

As you study for the PMI-RMP exam, ensure to become proficient in these skills, as they are critical to both passing the exam and being a competent risk management professional.

Answer the Questions in Comment Section

True or False: Risk weighting involves assigning a numerical value to each identified risk based on its magnitude and probability of occurrence.

  • True
  • False

Answer: True

Explanation: Risk weighting is the practice of assigning a numerical value to each risk identified in risk management, based on its magnitude and potential impact on a project.

Which of the following factors are considered when calculating risk priority?

  • a) Impact of the risk
  • b) Probability of the risk occurring
  • c) Risk response strategies
  • d) Both a and b

Answer: d) Both a and b

Explanation: Risk priority is determined by both the impact of the risk, how detrimental it will be to the project, and the probability of the risk occurring. Risk response strategies are part of risk management, not risk prioritization.

True or False: The higher the risk priority number (RPN), the lower the priority of the risk.

  • True
  • False

Answer: False

Explanation: The higher the risk priority number (RPN), the higher the priority of the risk. Risks with high RPNs are prioritized and addressed first in risk management planning.

Which of the following is NOT a method used to perform risk weighting?

  • a) Risk Impact/Probability Chart
  • b) CPA (Critical Path Analysis)
  • c) FMEA (Failure Modes and Effects Analysis)
  • d) SWOT Analysis

Answer: d) SWOT Analysis

Explanation: Risk Impact/Probability Chart, CPA, and FMEA are methodologies used in risk management for analyzing and calculating risk. SWOT analysis is a strategic planning tool not typically associated with risk weighting.

True or False: All risks should be treated as external risks when performing risk weighting and calculation of risk priority.

  • True
  • False

Answer: False

Explanation: Some risks are internal, coming from within the project or organization, while others are external, originating from outside the organization. Both types should be considered when performing risk weighting.

What does the acronym RPN stand for in risk management?

  • a) Risk Probability Number
  • b) Risk Priority Number
  • c) Risk Potential Number
  • d) Risk Performance Number

Answer: b) Risk Priority Number

Explanation: In risk management, RPN stands for Risk Priority Number. It’s a product of a risk’s severity, occurrence, and detection rating, and guide risk management efforts.

True or False: The probability of a risk is subjective and can vary depending on the perception of the risk manager.

  • True
  • False

Answer: True

Explanation: Probability is an estimated measure and varies based on available data and the perception of the risk manager. It isn’t a concrete or fixed value.

Which of the following is crucial to calculate risk priority?

  • a) Identifying risks
  • b) Analyzing risks
  • c) Planning risk responses
  • d) All of the above

Answer: d) All of the above

Explanation: All of these steps are critical in the process of calculating risk priority. Identification uncovers risks, analysis weighs them, and planning responses is an outcome of the prioritization process.

Risk weighting helps in determining:

  • a) The most critical risks
  • b) Least critical risks
  • c) Both a and b
  • d) None of the above

Answer: c) Both a and b

Explanation: Through risk weighting, a project manager can identify the most critical risks to address immediately and also the least critical risks, which can be monitored.

True or False: Calculating risk priority number (RPN) is a standard process for all types of risks.

  • True
  • False

Answer: False

Explanation: The calculation of RPN may not be suitable for all risk types as it largely depends on the nature of the risk and the contexts in which it arises. Different risks may require different methodologies for assigning priority.

0 0 votes
Article Rating
Subscribe
Notify of
guest
22 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments
Olivia Smith
8 months ago

Great post on risk weighting and calculating risk priority! Helped me for my PMI-RMP exam prep.

Walther Harth
7 months ago

Nice blog. Can anyone explain the difference between risk weighting and risk scoring?

Debbie Rogers
7 months ago

I appreciated the detailed explanation on how to calculate risk priority. Makes it easy to understand.

Nelly Villareal
8 months ago

What tools or software do you guys recommend for effective risk weighting?

Graciela Véliz
8 months ago

Great resource! Helped clarify the quantitative techniques for risk assessment.

Lois Heffels
6 months ago

Can anyone share their experience with heuristic approaches in risk weighting?

Deniz Yalçın
8 months ago

Where can I find more practice questions for the PMI-RMP exam?