Concepts

It requires thorough knowledge of the related aspects involved. These activities have different steps to ensure that project risks are effectively identified, assessed, planned for, and controlled.

1. Establishing Risk Management Context:

  • The who: Project manager or Risk Manager.
  • The what: Determining the strategic and operational context in which the rest of the process will take place. Setting risk parameters and objectives.
  • The when: Performed at the initiation phase of a project.
  • The where: Mainly in project meetings, project charter discussions, and strategy sessions.
  • The how: This involves the use of stakeholder analysis, current situation analysis, and risk appetite statements, among other tools.

2. Identify Risks:

  • The who: Entire project team.
  • The what: Systematic identification of potential risks that could impact the project.
  • The when: Throughout the project lifecycle, but intensively at the project initiation and planning phases.
  • The where: Happens at the project site or in team meetings.
  • The how: Risk identification techniques such as brainstorming, Delphi technique, SWOT analysis, expert interviews, etc.

3. Risk Analysis:

  • The who: Risk management specialists or the project team members with risk management skills.
  • The what: Evaluating the likelihood and impact of identified risks.
  • The when: During the planning process and when new risks are identified.
  • The where: In risk management meetings, or risk analysis sessions.
  • The how: Using qualitative and quantitative risk analysis techniques like Probability and Impact Matrix, Monte Carlo Simulations etc.

4. Risk Response Planning:

  • The who: The project manager with the involvement of the whole project team.
  • The what: Developing strategies to reduce negative risks (threats) and enhance positives ones (opportunities)
  • The when: After risk analysis, and updated throughout the project lifecycle.
  • The where: Within project team meetings and stakeholder engagement sessions.
  • The how: This involves risk response strategies such as avoidance, transfer, mitigate, accept, exploit, enhance and share depending on whether the risk is a threat or opportunity.

5. Risk Monitoring and Control:

  • The who: The project manager, risk owner, and project control team.
  • The what: Involves tracking identified risks, monitoring residual risks, identifying new risks, executing risk response plans and evaluating their effectiveness throughout the project life cycle.
  • The when: Throughout the project life cycle from start to end.
  • The where: Part of regular reporting and project meetings this can be done on-site or virtually.
  • The how: Using risk audits, technical performance measurement, reserve analysis, status meetings among other methods.

Implementing the above steps is pivotal in risk management as each step reveals the proper strategy to be used. It is important to articulate these steps alongside the PMI-RMP to understand the entire risk control structure and process.

Using this framework in combination with the guide provided by PMI-RMP will allow any project or risk manager to navigate risk effectively. It will result in more successful projects with fewer surprises, ultimately increasing an organization’s performance level and its ability to fulfill the project objectives.

Answer the Questions in Comment Section

Risk identification is a nonessential part of risk management.

  • True
  • False

Answer: False

Explanation: Risk identification is a critical step in the risk management process. It involves identifying potential risks that could negatively impact key business initiatives or projects.

Risk assessment is conducted only once during a project lifecycle.

  • True
  • False

Answer: False

Explanation: Risk assessment is not a one-time activity. It is conducted throughout the project lifecycle to monitor and control risks.

Which of the following activities are key to risk management?

  • Risk Identification
  • Risk Quantification
  • Risk Response Planning
  • All of the above

Answer: All of the above

Explanation: Risk identification, quantification, and response planning are key activities involved in managing risks in a project, according to the PMI-RMP exam.

Who is primarily responsible for performing risk management activities?

  • Project Manager
  • Risk Manager
  • Stakeholders
  • All of the above

Answer: All of the above

Explanation: Risk management is a collaborative effort which involves the project manager, risk manager, and all stakeholders.

A risk register is not necessary in risk management.

  • True
  • False

Answer: False

Explanation: A risk register is an important tool in risk management that captures identified risks, their severity and the actions steps to be taken to mitigate them.

Risk reviews should be only be done at the beginning of a project.

  • True
  • False

Answer: False

Explanation: Risk reviews should be conducted regularly throughout the project lifecycle.

Which of the following strategies can be used to manage a risk?

  • Accepting the risk
  • Mitigating the risk
  • Transferring the risk
  • All of the above

Answer: All of the above

Explanation: Risk strategies include accepting, mitigating or transferring the risk, depending on the nature and impact of the risk.

Risk management only involves responding to negative risks or threats.

  • True
  • False

Answer: False

Explanation: Risk management also involves identifying and responding to positive risks or opportunities.

Who is involved in the decision-making process of risk response planning?

  • Project Manager only
  • Stakeholders only
  • Project Manager and Stakeholders
  • None of the above

Answer: Project Manager and Stakeholders

Explanation: Both the project manager and stakeholders are involved in the decision-making process of planning the response to risks.

Risk management doesn’t need to be documented.

  • True
  • False

Answer: False

Explanation: Documentation is necessary in risk management to record identified risks, risk analysis results, risk response plan, and tracking of risk events.

Which tool does not help in risk management?

  • Risk Register
  • Project Charter
  • Stakeholder Register
  • None of the above

Answer: None of the above

Explanation: All of these are important tools used in risk management to capture necessary information regarding risks and stakeholders.

Risk communication should only happen after a risk has occurred.

  • True
  • False

Answer: False

Explanation: Risk communication should be on-going and proactive throughout the project, not just after a risk has occurred.

0 0 votes
Article Rating
Subscribe
Notify of
guest
23 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments
Sofie Mortensen
6 months ago

Great blog on the key risk management activities for the PMI-RMP exam!

Praneel Dalvi
8 months ago

Could anyone elaborate on the ‘Plan Risk Management’ process?

Felix Adams
6 months ago

Who is typically responsible for performing qualitative risk analysis?

Kai Opstal
8 months ago

When should risk identification occur in a project?

سارینا کوتی
6 months ago

Does anyone have experience with quantitative risk analysis techniques?

Jozef Veltmaat
8 months ago

Thanks for the helpful post!

Keith Rhodes
7 months ago

Where should risk management activities take place?

Antonios Reichert
6 months ago

How can we ensure all stakeholders are engaged in the risk management process?

23
0
Would love your thoughts, please comment.x
()
x