Concepts

Executing a risk response plan is an integral part of the project management cycle, particularly in relation to the PMI Risk Management Professional (PMI-RMP) examination. It involves identifying, assessing, and responding to project risks to reduce their potential impact on project objectives.

I. Risk Response Strategies

Risk response strategies fall into the following categories: avoid, mitigate, transfer, and accept.

  1. Avoid: The objective is to alter the project plan to eliminate the risk or to protect the project objectives from its impact. It usually involves changing the project management plan. Example: If there is a risk that a required component may not be available from a supplier, one could choose another supplier or reduce the components needed.
  2. Mitigate: The aim is to reduce the probability of occurrence or the impact of a risk to an acceptable threshold. Mitigation might involve developing an alternative solution or selecting the most effective approach to accomplish a project activity. Example: If there’s a risk of potential time delays, a project manager could mitigate that risk by arranging for additional resources.
  3. Transfer: This is aimed at relocating the liability for a risk to another party. It doesn’t eliminate the risk, but it does shift the responsibility. Example: Insurance is a means of transferring risk where an insurer assumes the risk for a premium.
  4. Accept: This means that the project team decides to acknowledge the risk and not take any action unless the risk occurs. This strategy is often used for risks with low impact and low probability. Example: Certain equipment might fail occasionally. If the potential delay isn’t too serious and the equipment can be quickly replaced or repaired, the team might choose to accept the risk.

II. Executing The Risk Response Plan

After the initial risk analysis, the risk response plan should be executed and monitored. Here are some key steps:

  1. Implement Risk Responses: This involves executing the risk response strategy that has been planned for. This could include avoiding the risk, mitigating it, transferring risk, or accepting it.
  2. Monitor Risks: According to the PMI, monitoring risks is an ongoing procedure that involves tracking identified risks, monitoring the remaining risk exposure, identifying new risks, and evaluating the effectiveness of the risk response plan.

III. Case Study: X Corporation

Let’s look at a practical example with X Corporation. X Corporation planned a new software implementation. They identified potential risks including delay in delivery, software bugs, and overrunning costs. The project team came up with the following risk responses:

  • Delay in Delivery: They decided to mitigate this risk by scheduling more testing and integration time into the project plan.
  • Software Bugs: The project team planned to both mitigate and transfer. Mitigation involved extensive quality control and testing. Transfer involved service level agreements (SLA) with the software development company for bug fixes and patches.
  • Overrunning Costs: To avoid this risk, the project team decided to work with a capped pricing model with the software company. Capital expenditure was also closely controlled and monitored.

During execution, they were continuously monitoring and controlling these risks. Their planned responses were implemented and adjusted as needed, enabling the project to achieve its objectives.

In conclusion, executing the risk response plan is a systematic approach to assessing and addressing project risks. It forms an essential part of the PMI-RMP exam and assures project success in real-world scenarios. By understanding the strategies for risk response; avoid, mitigate, transfer, and accept – project managers are equipped with the tools they need to manage potential project risks effectively.

Answer the Questions in Comment Section

True or False: The risk response plan is mainly concerned with determining how to reduce threats related to project risks.

  • True
  • False

Answer: True

Explanation: The risk response plan is part of risk management that aims at reducing threats associated with project risks and maximizing opportunities.

In the process of executing a risk response plan, the project manager should consider:

  • a) Altering the budget
  • b) Adjusting the project schedule
  • c) Communicating the plan to stakeholders
  • d) All of the above

Answer: d) All of the above

Explanation: A comprehensive risk response plan may require alterations to the budget or schedule, and it’s essential that stakeholders are properly informed about these changes.

True or False: A proper risk response plan doesn’t require any contingencies.

  • True
  • False

Answer: False

Explanation: Any solid risk response plan should include contingencies. These are provisions for unforeseen events or circumstances that can help minimize potential impact.

The process of developing options and decisions to enhance opportunities and reduce threats related to project objectives is known as:

  • a) Risk identification
  • b) Risk response planning
  • c) Risk analysis
  • d) None of the above

Answer: b) Risk response planning

Explanation: The definition provided is that of risk response planning.

True or False: Active acceptance of risks is a risk response strategy.

  • True
  • False

Answer: True

Explanation: Active acceptance is a strategy where the project team decides to acknowledge the risk and develop a contingency response plan.

The risk response plan must address:

  • a) Both negative and positive risks
  • b) Only negative risks
  • c) Only positive risks
  • d) None of the above

Answer: a) Both negative and positive risks

Explanation: A good risk response plan should cover both negative (threats) and positive (opportunities) risks.

Contingency plans are developed for risks that have been:

  • a) Transferred
  • b) Accepted
  • c) Mitigated
  • d) Ignored

Answer: b) Accepted

Explanation: Contingency plans are typically developed for those risks that have been accepted and are likely to have an impact on project objectives.

Which of the currently identified risks need special contingency and response team based on the risk rating?

  • a) High risk
  • b) Medium risk
  • c) Low risk
  • d) Both a and b

Answer: a) High risk

Explanation: Typically, high risks need special contingency plans and dedicated response teams in place as they pose significant potential threats to the project.

True or False: The risk response plan should be included in the project planning documents.

  • True
  • False

Answer: True

Explanation: The risk response plan is a critical aspect of project management. It should be part of the project planning documents so all parties involved are aware of the possible risks and their planned responses.

Who is responsible for implementing risk responses?

  • a)Project team
  • b)Project manager
  • c)Risk owner
  • d)All of the above

Answer: d)All of the above

Explanation: Every person involved in a project has some level of responsibility in implementing risk responses, depending on the nature and level of the risks involved.

0 0 votes
Article Rating
Subscribe
Notify of
guest
20 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments
Patsy Brewer
6 months ago

Great post on executing the risk response plans! It really helped clarify some points for me.

Jesse Salonen
8 months ago

I appreciate the detailed explanation. It’s important to monitor risk responses regularly.

Danijela Leroy
6 months ago

One thing I’d like to add is the importance of updating the risk register in sync with the response plan execution. Thoughts?

Gabriel Lévesque
8 months ago

Thanks for the post! It was very informative.

Liam Lavoie
9 months ago

When executing risk responses, how do you document the changes made to the project plan?

Alwine Graupner
8 months ago

This blog helped me understand how to prioritize risk responses. Thanks!

Bariş Nieuwenburg
5 months ago

There seems to be a typo in the second paragraph. Thought I’d point it out.

Malou Mortensen
8 months ago

Can anyone share best practices for integrating risk responses into daily project tasks?

20
0
Would love your thoughts, please comment.x
()
x