Concepts
It’s when the deliverables are transferred to their respective stakeholders, the project/phase closure report is prepared, and the project resources are released. The Project Management Professional (PMP) Exam explicitly discusses project or phase closure, ensuring candidates comprehend these concepts. The broad aspects of project or phase closure are planning and managing.
Planning Project or Phase Closure:
The closure stage is much more than just concluding a project or phase. It necessitates complete documentation that reflects the project’s entire journey. A crucial aspect of successful project and phase closure is planning, which should incorporate the following elements:
- Project deliverables: Here, we need to affirm that the deliverables of the project align with the project’s initial scope, quality and are ready to be transferred to the correct stakeholders.
- Project performance documentation: Ensure that the project’s successes and failures are properly documented, proving beneficial for prospective projects.
- Release resources: Resources with project commitments like team members, hardware, software, machinery, and facilities should be discharged systematically.
- Vendor contract closures: All external vendor contracts should be formally closed.
Managing Project or Phase Closure:
Transitioning of deliverables: The finalized project deliverables are handed over to the correct stakeholders, with significant consideration provided to the transition process to ensure a seamless move.
Final project report: A final report of the project’s performance, including its budgeting, scheduling, scope, and quality, should be documented. This helps analyze the project as a whole and provides insights.
Post-project review: A comprehensive review of the project’s outcome helps identify its successes and failures. It aids in identifying lessons learned and incorporating them into future ventures.
Project Archive: Creating a project archive that chapterizes all project documents, artifacts, and tools utilized during the project is a fundamental part of managing project closure.
Celebration: Recognizing team efforts and accomplishments can boost morale and act as positive reinforcement.
Example:
Let’s look at an example of a software development project. In the planning phase of project closure, the project manager checks the final software against the original scope, ensures that all features are working fine and are ready to be handed over to the client. All the signed contracts with external vendors, such as cloud service providers, are closed.
Managing the project closure involves transitioning the software to the client’s environment, providing all necessary documentation, training, and handover procedures. A final report is then drafted where the project completion time, budget, and quality are compared against the plan. A post-project review is done to learn the lessons and to formulate recommendations for future projects. All these items are then archived. Lastly, a project success celebration is organized to recognize the team effort.
Overall, project or phase closure is an essential element of project management that must be carefully planned and managed for a successful project completion. Moreover, its importance has been underlined in the PMP exam, necessitating its comprehensive understanding. By meticulously planning and managing project/phase closure or transitions right, organizations will benefit from efficient resource utilization, better stakeholder management, and continuous improvement.
Answer the Questions in Comment Section
True/False: The project closure phase is the last phase in the project management life cycle.
- True
- False
Answer: True
Explanation: The project closure is the final phase of the project life cycle that includes closing all aspects of the project and handing over the deliverables.
In which phase is a project shift from execution to closure defined?
- a) Initiation
- b) Planning
- c) Execution
- d) Controlling and Monitoring
- e) Closure
Answer: e) Closure
Explanation: The shift from execution to closure is defined in the closure phase itself where the project manager ensures all project work is completed and the project purpose has been achieved.
True/False: A project transition plan is not necessary for every project.
- True
- False
Answer: False
Explanation: A project transition plan is essential for every project as it guides on how to shift the project deliverables to the operations team or the client.
Which document should be finalized during the project closure phase?
- a) Project plan
- b) Risk register
- c) Stakeholder register
- d) Project documents
Answer: d) Project documents
Explanation: All project related documents should be finalized, updated and archived for future reference during the project closure phase.
During project/phase closure, what is not considered as an essential task?
- a) Updating the lessons learned register
- b) Releasing the project team
- c) Updating the project charter
- d) Documenting project success or failure.
Answer: c) Updating the project charter
Explanation: The project charter is created in the initiation phase and is not usually updated during the closure phase.
True/False: It is necessary to get formal sign-off from the client during project/phase closure.
- True
- False
Answer: True
Explanation: Getting formal sign-off from the client is essential during project/phase closure to seal the completion and acceptance of the project.
Who is responsible for handling the project closure phase?
- a) Sponsor
- b) Client
- c) Project Manager
- d) Stakeholders
Answer: c) Project Manager
Explanation: The project manager is responsible for all phases of the project including closure.
The lessons learned register should be updated:
- a) During project/phase closure only
- b) At the end of each process/phase
- c) At the initiation phase
- d) There is no need to update the lessons learned register
Answer: b) At the end of each process/phase
Explanation: Lessons learned should be documented throughout the project to capture what worked well and what didn’t, for future similar projects.
True/False: The project/phase closure phase should only start once all project deliverables have been completed.
- True
- False
Answer: False
Explanation: The project/phase closure phase can start even if some minor tasks and deliverables are still being finalized.
The main purpose of the project closure phase is to:
- a) Add more features to the project
- b) Ensure all project deliverables have been completed and handed over successfully
- c) Plan for the next project
- d) Analyze the need for the project
Answer: b) Ensure all project deliverables have been completed and handed over successfully
Explanation: The main goal of project closure is to ensure all tasks were accomplished, and deliverables are ready to be handed over to either the daily operations team or the client.
This blog post is incredibly informative. Project/phase closures are often underestimated.
I appreciate the detailed steps provided for project closure. Really helps with PMP preparation.
I find it useful to have a checklist during project closure to ensure all tasks are completed.
Great insights on transitioning to operations! This is critical for maintaining project benefits.
Thanks for the post! It clarified a lot of my doubts on phase closures.
Correct documentation during project closure is key. Any recommended tools?
The templates shared here are invaluable. Thanks a ton!
What are some challenges you’ve faced during project closure?